Cashman Equipment Corp. was contracted by Sarens USA in September 2020 to charter two 250’ Class ABS deck barges, the JMC 256 and JMC 259, to support the removal of the Green Crane at Newport News Shipyard (NNS). Sarens USA was awarded this Contract in July 2019. NNS is dedicated to the US Navy providing maintenance support, as well as…
Cashman Equipment Corp., is pleased to announce the continued expansion of its global barge fleet with the addition of three large ballastable deck barges, measuring 330’ x 100’ x 20’. The newly acquired barges, named the JMC 3339, JMC 3340 and JMC 3341, are currently based within Cashman Equipment’s Gulf of Mexico fleet and are available for worldwide deployment.
The…
Cashman Equipment Corp. is pleased to announce the continued expansion of its North American fleet with the addition of 14 open hopper barges. These 14 hopper barges are 200’ x 35’ x 12’ and are based within Cashman Equipment Corp.’s Louisiana, USA fleet. Barges are available now for local projects or worldwide deployment.
Cashman Equipment Corp., a global…
Location: Coatzacoalcos, Mexico
Servicio Marina Superior (SMS), the affiliate towing company of Cashman Equipment, recently completed a project with our client to supply two tug boats to support the pipe laying vessel Samson working in Coatzacoalcos, Mexico. SMS supplied the 3600HP tug boats M/V REED DANOS and M/V TODD DANOS to tow Cashman Equipment barges loaded with pipe from the shore to the…
Location: Caspian Sea
Client: ERSAI
In October 2008 Cashman Equipment Corp. (CEC) was contracted by Ersai to design, construct, deliver and operate two Floatels. Each vessel was required to provide a minimum POB of 250. The marine accommodation vessels were required to be fully autonomous for a minimum of 12 days on location. Cashman Equipment constructed 90% of both vessels in Amelia, Louisiana. This work took…
Location: Cuba
Client: Titan Salvage
In September 2012, Cashman Equipment supported TITAN Salvage’s emergency response to a container ship grounded in Cuba. The containership was en route from Santiago de Cuba to Havana, Cuba, when it came ashore after losing power during Tropical Storm Isaac in late August. Following the grounding, TITAN contracted with Cashman Equipment to provide a deck barge for lightering of cargo and to support the…
Location: Tiverton-Portsmouth, Rhode Island
Client: Cardi Corporation
Contract Amount: $34,600,000
The project consisted of the installation of foundation support systems for the Sakonnet River Bridge Project which included furnishing and installing approximately 7,338 LF of 72” pipe piles within the Sakonnet River, as well as, furnishing and installing approximately 51,525 LF of H-Section Steel Piles for the land-based foundations. The installation of the 72” pipe piles required the design…
Location: Jamestown, Rhode Island
Client: Rhode Island Department of Transportation
Contract Amount: $20,500,000
The project consisted of demolishing and disposing of the Old Jamestown Bridge between the towns of North Kingstown and Jamestown in Rhode Island. The demolition portion of this contract was approximately 5,332 feet of bridge spanning the West Passage of Narragansett Bay and included the removal and disposal of 6,000 tons of steel and 38,000 cubic yards of concrete.
…
Location: San Juan, Puerto Rico
Client: U.S. Army Corps of Engineers
Contract Amount: $27,500,000
This project was located in San Juan, Puerto Rico. This heavy and marine construction project involved pile load testing, pile driving of 18” diameter pipe piles for foundation support for structures, concrete piles, 48” diameter pipe piles with steel sheet diaphragms for cantilever retaining walls along the Puerto Nuevo River retaining a highway on one side of the river…
Location: Boston, Massachusetts
Client: Massachusetts Water Resources Authority
Contract Amount: $27,700,000
This project involved construction of the pier and bulkhead facility on Deer Island, The pier was founded on pipe piles with a cast-in-place concrete deck and included two roll-on roll-off bridges that allowed trucks arriving by barge to drive directly off barges. The bulkhead was constructed of steel sheet piling with a concrete relieving platform built behind the bulkhead.…
Location: Boston, Massachusetts
Client: Massachusetts Water Resources Authority
Contract Amount: $77,000,000
Work related to this project included the installation of 55, 250’ long, 30-inch diameter and 1¾-inch wall thickness FRP risers, lowered and grouted into a predrilled shaft in the seabed. Each riser was capped with a diffuser consisting of a concrete base latched onto a steel casing grouted to the bedrock, an 8 port FRP manifold cast into concrete,…
Location: Quincy, Massachusetts
Client: Commonwealth of Massachusetts
Contract Amount: $819,000
This job included the dredging of approximately 70,000 cubic yards of material including an entrance channel, transition area and mooring/docking basin by mechanical method with open sea disposal of the dredged material. Difficulties included dredging relatively shallow depths (to -7' below low water) and working with a 10' tide range.
Location: Quonset Point, Rhode Island
Client: Horizon Offshore
Contract Amount: $2,200,000
The work associated with this project was part of the Northeast Gateway Project. Cashman Equipment Corp. was hired to transport 18” and 24” concrete coated pipe to Pier 2 in Quonset Point, Rhode Island and load the pipe in a sequence determined by Horizon Offshore onto ABS barges.
Location: Boston, Massachusetts
Client: Duke Energy Gas Transmission Line
Contract Amount: $5,000,000
Cashman Equipment Corp. installed approximately 30 miles of 30” gas transmission pipe line offshore from Salem, Massachusetts to Weymouth, Massachusetts as a subcontractor to Stolt Offshore, Inc. Work performed by Cashman Equipment Corp. included loading pipe and materials on barges, underwater pipe pulling, dredging and backfilling.
Location: Quincy, Massachusetts
Client: Massachusetts Water Resources Authority
Contract Amount: $12,640,000
Work included two roll-on roll-off bridges that allowed trucks departing by barge to drive directly onto barges. The bulkhead was constructed of steel sheet piling with a concrete relieving platform built behind the bulkhead. This construction also included dredging and a large paved parking / staging area and access roads.
Location: Boston, Massachusetts
Client: Massachusetts Highway Department
Contract Amount: $35,842,000
This was one of the early Central Artery/Tunnel projects (known unofficially as the Big Dig). This project involved construction of a pair of concrete combined sewer outfall lines. The outfall was a concrete structure approximately 17 feet wide and 14 feet in height and a combined length of 5200 LF. Part of this outfall was constructed as a post-tensioned prestressed…
Ubicación: Louisiana
Cliente: Bois D'Arc
Importe del Contrato: $3,000,000
Este proyecto incluyó la instalación de pilotes de Madera alrededor de los cabezales de pozos existentes en 8 ubicaciones distintas (se instalaron 48 pilotes). Adicionalmente, se instalaron vigas de 12” X 8” alrededor del pilotaje en tres elevaciones distintas en cada pozo para proteger los pozos productores. Cashman Equipment instaló también bases para rejillas y luces. Adicionalmente, Cashman Equipment instaló…
Location: Black Bay, Louisiana
Client: Petro Construction
Contract Amount: $350,000
Project involved working as directed alongside Helis Central Facility in Black Bay, Louisiana. The JMC 86 (a 4100 Manitowoc/ Ringer mounted on a 250' x 72' deck barge) was utilized to set all heavy production equipment, cross over bridges, compressors and rig mounted hydraulic cranes. Production equipment was transported to Black Bay on Cashman Equipment deck barges and was then lifted into…
Location: Boston, Massachusetts
Client: Massachusetts Water Resources Authority
Contract Amount: $49,800,000
Work involved the excavation and movement of approximately 4,000,000 cubic yards of glacial till and 1,400,000 tons of tunnel muck. By the conclusion of the porject, Cashman Equipment had removed approximately 2,000,000 cubic yards of glacial till from Deer Island, with most of that material being used as capping material for landfills.
Location: West Cameron, Louisiana
Client: Callon Petroleum
Contract Amount: $400,000
Project involved fabricating piling jigs and installation of one (6) pile well protector. One 48'x120' pile for helideck and one (8) pile platform for production equipment. All work was done on location in West Cameron Block 2 of the Gulf of Mexico. Cashman Equipment Corp. installed all piles and then installed pre-fabricated platforms into positions as well as installing two connecting bridges…
Location: Various Locations in Massachusetts
Client: Massachusetts Turnpike Authority
Contract Amount: $8,360,000
Work involved bridge deck and highway reconstruction at several Massachusetts locations including Newton, Weston, Framingham and Grafton.
Location: Boston, Massachusetts
Client: Massachusetts Water Resources Authority
Contract Amount: $22,972,000
Work involved demolition of the old prison and the old World War II concrete bunker fortification.