Location Quincy, Massachusetts
Client Commonwealth of Massachusetts
Contract Amount $819,000

This job included the dredging of approximately 70,000 cubic yards of material including an entrance channel, transition area and mooring/docking basin by mechanical method with open sea disposal of the dredged material.  Difficulties included dredging relatively shallow depths (to -7' below low water) and working with a 10' tide range.